| 4 | +# Cycle 1 — delivery guide and Scrum working agreement |
| 5 | + |
| 6 | +## Document control |
| 7 | + |
| 8 | +| Field | Value | |
| 9 | +|---|---| |
| 10 | +| Package | PyBLE 2026 Q4 reliable workflow, Cycle 1 (`C1`) | |
| 11 | +| Prepared | 25 September 2026; Asia/Bangkok | |
| 12 | +| Strategy | [Implementation Plan, revision 1.2](../../planning/PyBLE_Implementation_Plan_and_Strategy_v1.0.md) | |
| 13 | +| Repository baseline | `23ed764b0ef88dce9720c66fbd1c0655268860cf` | |
| 14 | +| Proposed cycle | 28 September–20 December 2026; six two-week Sprints | |
| 15 | +| Status | Proposed delivery package; no Sprint Planning, estimates, named assignments, implementation approval, or new physical results are implied | |
| 16 | +| Primary audience | Tablet-owning makers, provisionally; confirm one reachable cohort before observation | |
| 17 | +| Authoritative contracts | [Contributor rules](../../../AGENTS.md), [App specification](../../specifications/App/specs.md), [App TDD](../../specifications/App/TDD.md), [PBLE/1](../../specifications/protocol.md), and applicable firmware/release specifications | |
| 18 | + |
| 19 | +This package derives execution views from the strategy. It does not replace normative specifications, expand hardware claims, create GitHub issues, or authorize store/website publication. The strategy file is currently a local document; include it with this package when proposing the documentation for version control. |
| 20 | + |
| 21 | +## Navigation and ownership of information |
| 22 | + |
| 23 | +| File | Canonical responsibility in this package | Update trigger | |
| 24 | +|---|---|---| |
| 25 | +| [01 — Overview and Scrum framework](01_Overview_and_Scrum_Framework.md) | Product Goal, working agreement, quality and evidence rules | Agreement or governing contract changes | |
| 26 | +| [02 — Product roadmap](02_Product_Roadmap.md) | Outcomes, horizons, and conditional investments | Product Goal or strategic priority changes | |
| 27 | +| [03 — Milestones](03_Milestones.md) | Evidence-based decisions and admission criteria | New evidence or a milestone decision | |
| 28 | +| [04 — Sprint plan](04_Sprint_Plan.md) | Sprint Goal forecasts, calendar, and capacity | Sprint Planning or Sprint Review | |
| 29 | +| [05 — Product backlog and stories](05_Product_Backlog_and_Stories.md) | Ordered work, parent/child identities, acceptance criteria, and source traceability | Refinement or changed user evidence | |
| 30 | +| [06 — Sprint backlogs](06_Sprint_Backlogs.md) | Candidate tasks, local effort allowances, dependencies, and execution status | Developers select/adapt work during a Sprint | |
| 31 | + |
| 32 | +```mermaid |
| 33 | +flowchart LR |
| 34 | + Strategy["Strategy revision 1.2"] --> Goal["One Product Goal"] |
| 35 | + Goal --> Roadmap["Outcome roadmap and milestones"] |
| 36 | + Roadmap --> Product["Ordered Product Backlog"] |
| 37 | + Product --> Planning["Sprint Planning"] |
| 38 | + Planning --> Sprint["Sprint Goal and Sprint Backlog"] |
| 39 | + Sprint --> Increment["Increment meeting Definition of Done"] |
| 40 | + Increment --> Review["Sprint Review: inspect evidence"] |
| 41 | + Review --> Product |
| 42 | + Review --> Roadmap |
| 43 | + Sprint --> Retro["Retrospective: improve how we work"] |
| 44 | + Retro --> Planning |
| 45 | +``` |
| 46 | + |
| 47 | +## Product Goal and current baseline |
| 48 | + |
| 49 | +**Proposed Product Goal:** tablet-owning makers can complete useful BLE board work, recover their local work after interruption, and choose PyBLE again for a relevant task using accurately identified app and firmware builds. |
| 50 | + |
| 51 | +| Active outcome | Main planning parents | Evidence of value | |
| 52 | +|---|---|---| |
| 53 | +| Know what users install | PYB-001; residual PYB-002 only | Reproducible installation guidance and dated channel/build evidence | |
| 54 | +| Preserve users' work | PYB-006, supported by PYB-008/009 | Accepted draft survives the specified restart/failure cases without implicit board writes | |
| 55 | +| Complete useful repeat tasks | PYB-003/004/011/012; PYB-005 if observed | Task C attempts, later-day useful work, reasons to choose PyBLE, and support effort | |
| 56 | + |
| 57 | +| Baseline fact | Consequence | |
| 58 | +|---|---| |
| 59 | +| Android open-testing copy correction is complete in PR #33 | Do not replan that correction; identify any new discrepancy separately | |
| 60 | +| App source is `0.2.0+8`; Play publicly identifies `0.2.0`; iPad remains external TestFlight beta | Source version does not prove the installed store binary or its source commit | |
| 61 | +| Firmware v0.6.1 is published on owner confirmation across five exact profiles | Pending automated results stay pending; no automatic PyBLE Ready badge | |
| 62 | +| Issue #24 is closed/superseded | Do not resurrect its old release umbrella as a dependency | |
| 63 | +| Editor draft is volatile under [ADR-0010](../../decisions/0010-working-loop-in-memory-document.md) | Close an accepted subset of A-24; do not claim full project persistence or Blocks recovery | |
| 64 | +| Lifecycle protections, tutorials, imports, and test tools already exist | Reuse them; refine only observed gaps and the documented persistence gap | |
| 65 | + |
| 66 | +## Applying Scrum to PyBLE |
| 67 | + |
| 68 | +The [2020 Scrum Guide](https://scrumguides.org/scrum-guide.html) is the framework reference. The Product Backlog is ordered by the Product Owner; Developers select and adapt Sprint work. Product Goal, Sprint Goal, and Definition of Done guide the respective artifacts. A Sprint Review inspects progress and informs adaptation; it is not a mandatory release approval meeting. Roadmaps, milestones, user-story notation, and hour allowances below are PyBLE planning practices, not additional Scrum requirements. |
| 69 | + |
| 70 | +| Accountability | Proposed PyBLE arrangement | Assignment state | |
| 71 | +|---|---|---| |
| 72 | +| Product Owner | One maintainer accountable for the Product Goal, backlog order, and stakeholder tradeoffs | Named person TBD | |
| 73 | +| Scrum Master | Facilitates effective Scrum, impediment removal, and sustainable delivery | Named person TBD; any combined responsibility must be explicit | |
| 74 | +| Developers | Contributors collectively plan and deliver work, including applicable tests and evidence | Actual availability and skills TBD | |
| 75 | +| Stakeholders/contributors | Release owner, board operator, pilot coordinator, instructor, and language reviewer supply expertise/access | These contribution responsibilities do not create extra Scrum accountabilities | |
| 76 | + |
| 77 | +Do not represent a solo-maintainer workflow with missing accountabilities as a fully staffed Scrum Team. Record the practical arrangement and its limits. Role labels in tables are suggestions, not assignments to absent people. A coding agent does not supply independent physical evidence or become the accountable Product Owner. |
| 78 | + |
| 79 | +| Event/practice | Proposed local cadence | Concrete output | Capacity treatment | |
| 80 | +|---|---|---|---| |
| 81 | +| Sprint Planning | First working day; initially allow 60 minutes | One Sprint Goal, selected items, task plan, named capacity and dependencies | Inside the Sprint's gross hours | |
| 82 | +| Daily Scrum | 15 minutes each working day | Developers inspect the Goal and adapt the immediate plan | Inside the Sprint's gross hours | |
| 83 | +| Sprint Review | Last working day; initially allow 60 minutes | Inspect usable Increment and evidence with stakeholders; adapt backlog | Inside the Sprint's gross hours | |
| 84 | +| Sprint Retrospective | After Review; initially allow 45 minutes | One improvement to apply in the next Sprint | Inside the Sprint's gross hours | |
| 85 | +| Refinement | Up to one hour weekly initially, adjusted to need | Split/clarify upcoming items; Developers size their work | Included within available capacity; no separate approval ceremony | |
| 86 | + |
| 87 | +These local durations can change with the team; the Daily Scrum remains 15 minutes. The 14-hour reserve per Sprint includes events, refinement, support, additional qualification, and uncertainty. Do not count those hours again as extra delivery capacity. |
| 88 | + |
| 89 | +## Local readiness and Definition of Done |
| 90 | + |
| 91 | +| Before selection: local readiness aid | Required clarification | |
| 92 | +|---|---| |
| 93 | +| User outcome or learning question | Named beneficiary, observed problem, bounded in/out scope | |
| 94 | +| Governing contract | Specification/ADR and prior approval required for behavior changes; any carried exception visible | |
| 95 | +| Acceptance and evidence | Observable scenarios, relevant tests, physical devices when required, evidence location | |
| 96 | +| Feasibility | Developers' estimate, actual owner/access, dependencies, safe rollback/recovery | |
| 97 | + |
| 98 | +Readiness is a local refinement aid. It does not replace Sprint Planning or add a formal Scrum commitment. Unknowns can be selected as time-boxed discovery items with their own explicit output. |
| 99 | + |
| 100 | +| Definition of Done: applicable requirement | Evidence required | |
| 101 | +|---|---| |
| 102 | +| Behavioral scope agrees with the accepted contract | Specification/ADR changed before implementation where required; all selected acceptance scenarios satisfied | |
| 103 | +| Behavior is verified | Required `[red]` then `[green]` work, relevant regression checks, and mandatory physical evidence for the selected scope; refactor only while green | |
| 104 | +| Repository boundaries hold | DCO-signed commits when committing; no-leak, license, dependency, localization/import, and actual required CI checks as applicable | |
| 105 | +| Increment is coherent and usable | Review completed; integration and relevant documentation agree; no unresolved blocking data-loss or unintended-write defect | |
| 106 | +| Claims have evidence | Exact artifacts, pass/fail/not-run states, limitations and pending release work recorded truthfully | |
| 107 | +| Documentation/discovery scope is complete | Usable reviewed record/guide or agreed findings, source/link checks, and explicit unmet targets; no invented physical results | |
| 108 | + |
| 109 | +This is the proposed package-wide minimum; accepted normative requirements remain binding. Apply it to the selected item rather than treating a source merge as a finished feature. A documentation or discovery item can be Done with a negative finding, while a required physical-installation task cannot be Done if no installation happened. A usable Sprint 1 documentation increment should help an operator or user perform the current workflow; an internal plan alone is not evidence of improved app behavior. |
| 110 | + |
| 111 | +| State distinction | Meaning | |
| 112 | +|---|---| |
| 113 | +| Source complete | Implementation/review work reached its source milestone; required physical or integration work may still prevent Done | |
| 114 | +| Done Increment | Selected acceptance and applicable Definition of Done are met; it can be inspected and used in its declared scope | |
| 115 | +| Release admitted | All applicable release-level gates, support matrix, provenance and distribution prerequisites pass | |
| 116 | +| Submitted / available / installed | Three different distribution observations, each requiring its own evidence | |
| 117 | + |
| 118 | +Unfinished items return to the Product Backlog for reordering and replanning. Do not count them as Done or convert a blocked result into a pass. A release can happen during any Sprint when its applicable gates pass; recruitment and retention do not block an otherwise qualified maintenance release. |
| 119 | + |
| 120 | +## IDs, evidence, and change control |
| 121 | + |
| 122 | +| Convention | Rule | |
| 123 | +|---|---| |
| 124 | +| `PYB-001` … `PYB-032` | Existing strategy planning parents; not GitHub issue numbers | |
| 125 | +| `PYB-006.1`, `PYB-006.2`, etc. | Derived child items in this package; acceptance is maintained in file 05 | |
| 126 | +| `A-24` | Existing broader persistence story; a bounded child does not complete all of it | |
| 127 | +| `C1-S1` … `C1-S6` | This cycle's Sprints; distinct from historical App TDD Sprint labels | |
| 128 | +| `C1-S1-T01`, etc. | Proposed task rows; not new public contracts | |
| 129 | +| `M-01`, etc.; `SG0` … `SG6` | Delivery milestones versus strategy gates; neither replaces CI G0/G1 or C3 firmware gates | |
| 130 | +| Item/task status | Proposed → Selected at Planning → In progress → Review → Done; Blocked records a reason/owner; later forecasts remain Proposed | |
| 131 | +| Private versus public records | Contact/consent, device identifiers and raw logs remain private/ignored; publish only reviewed aggregate findings and redacted evidence | |
| 132 | + |
| 133 | +When facts or priority change, update the canonical file above and its dependent tables together. Preserve old evidence and dated decisions. New opcode/capability values, hardware support, Ready awards, and publication need their normal specification and authorization paths; none is inferred from this package. |
| 134 | + |
| 135 | +## Source map |
| 136 | + |
| 137 | +| Source | Use and precedence | |
| 138 | +|---|---| |
| 139 | +| [Strategy revision 1.2](../../planning/PyBLE_Implementation_Plan_and_Strategy_v1.0.md) | Scope, targets, six-Sprint capacity, three outcomes, Ready program and conditional horizons | |
| 140 | +| [Public roadmap](../../ROADMAP.md), [README](../../../README.md) | Current capability and distribution baseline | |
| 141 | +| [App specification](../../specifications/App/specs.md), [App TDD](../../specifications/App/TDD.md), [ADR-0010](../../decisions/0010-working-loop-in-memory-document.md) | Persistence contract and recorded implementation deviation; consult frozen working-loop scope | |
| 142 | +| [Firmware roadmap](../../planning/firmware-v0.6.1-v0.7.0-roadmap.md), [PBLE/1](../../specifications/protocol.md) | v0.7 proposals versus frozen wire behavior; old v0.6.1 publication/#24 wording is historical | |
| 143 | +| [Android publication review](../../testing/website/android-open-testing-2026-09-25.md), [v0.6.1 publication record](../../testing/firmware-v0.6.1-publication-2026-09-11.md) | Dated evidence; neither establishes a newly installed binary or missing automated qualification | |
| 144 | +| [HIL guide](../../../tests/firmware_tests/hil/README.md), [CI workflow](../../../.github/workflows/ci.yml), [CONTRIBUTING](../../../CONTRIBUTING.md) | Reuse existing tools and gates; actual CI requirements govern merges | |