5 | 5 |
|
6 | 6 | | Control | Value | |
7 | 7 | |---|---| |
8 | | -| Status | M-01/SG0 remains Blocked on 25 September by pilot ownership/cohort/setup and capacity decisions; existing channel installations verified on retry. M-02 is in progress in the 31 October candidate with acceptance pending; other milestones remain Proposed and forecast windows need replanning | |
| 8 | +| Status | M-01/SG0 remains Blocked on 25 September by pilot ownership/cohort/setup and capacity decisions; existing channel installations verified on retry. M-02 is in progress in the 31 October candidate with acceptance pending; M-04/M-05 artifact and distribution preparation is underway, with admission and channel delivery still pending; forecast windows need replanning | |
9 | 9 | | Planning date | 25 September 2026; dates use Asia/Bangkok | |
10 | | -| Source | [Implementation strategy revision 1.6](../../planning/PyBLE_Implementation_Plan_and_Strategy_v1.0.md), especially §§4, 8–10, 14, and 19 | |
| 10 | +| Source | [Implementation strategy revision 1.7](../../planning/PyBLE_Implementation_Plan_and_Strategy_v1.0.md), especially §§4, 8–10, 14, and 19 | |
11 | 11 | | Inspected baseline | `main` at `23ed764b0ef88dce9720c66fbd1c0655268860cf` | |
12 | 12 | | Related documents | [Framework](01_Overview_and_Scrum_Framework.md), [roadmap](02_Product_Roadmap.md), [Sprint Plan](04_Sprint_Plan.md), [stories](05_Product_Backlog_and_Stories.md), [Sprint Backlogs](06_Sprint_Backlogs.md) | |
13 | 13 | | Meaning | Milestones describe inspectable outcomes and decision evidence; they are not additional Scrum events or promised releases | |
14 | 14 |
|
15 | | -**31 October continuation update:** bounded recovery candidate `0.3.0+9` is merged in [PR #40](https://github.com/PyBLE-dev/PyBLE/pull/40) at `6f5b3ea`; the integrated suite and post-merge CI pass. Both tablets have local candidate installations and native storage restart evidence. [C1-S2 implementation record](c1-s2/00_Execution_Record.md) tracks the remaining physical acceptance separately from release qualification. S1 remains six Done / two Prepared / four Awaiting evidence. Original dates/hours remain the planning baseline; the current continuation order and unresolved capacity inputs are recorded in the [Sprint plan](04_Sprint_Plan.md#31-october-continuation-order-and-reforecast). |
| 15 | +**31 October continuation update:** the `0.3.0+9` recovery baseline merged in [PR #40](https://github.com/PyBLE-dev/PyBLE/pull/40). Physical qualification exposed three keyboard defects; their repairs at `bef67bd` pass 984 ordinary tests and all 36 PR #41 checks. iPad recovery, final keyboard regressions and all five iPad app-only board rows pass with declared source/firmware scope. Earlier Android recovery and board rows pass, but a later final-candidate Blocks startup observation remains under investigation. Signed packages and a channel packet are prepared; admission and actual store delivery remain separate. The [C1-S2 record](c1-s2/00_Execution_Record.md) binds the evidence. S1 remains six Done / two Prepared / four Awaiting evidence. Original dates/hours remain the baseline; the [continuation plan](04_Sprint_Plan.md#31-october-continuation-order-and-reforecast) records unresolved capacity inputs. |
16 | 16 |
|
17 | 17 | ## Assessment and evidence states |
18 | 18 |
|
@@ -49,8 +49,8 @@ no role in this table implies committed staffing or independent review. |
49 | 49 | | M-01 — Blocked (25 Sep) | Accepted baseline and bounded cycle scope make installation, pilot, and engineering decisions reproducible | C1-S1, 28 Sep–11 Oct; PYB-001/003/004, residual 002, sizing 006/009 | Dated channel/install/source mapping or explicit owned unknowns; one primary cohort/job; safe task/consent rules; initial observations or recruitment blocker; actual capacity; persistence and physical-matrix estimates | SG0: accept a bounded scope or record gaps; Product Owner with release, pilot, and Developers | |
50 | 50 | | M-02 — In progress; acceptance pending | A usable, bounded local-draft recovery increment protects accepted user work after interruption | C1-S2–C1-S3, 12 Oct–8 Nov; selected PYB-006 scope, supporting 009/008, observed 005 only if selected | Accepted App specification/TDD and ADR-0010 change; text/Blocks scope; persistence boundary; relaunch, interrupted-write, and corrupt-state scenarios; no implicit board overwrite/run; relevant regression and physical evidence | Review against the selected story acceptance criteria and Definition of Done; Developers with a named review path | |
51 | 51 | | M-03 — Proposed | Observed first-use and meaningful second-task evidence explains activation and its largest obstacle | C1-S4, 9–22 Nov; PYB-004/011 and justified 005/012 | Safe recorded pilot setup; at least 12 eligible primary-cohort task starts, all outcomes retained; successful unassisted timing; Task C attempts, prior workflow, assistance and reasons | SG2: assess provisional completion/timing targets and severe failures; pilot lead supplies evidence, Product Owner records next investment | |
52 | | -| M-04 — Proposed | A frozen maintenance candidate is qualified for its declared release scope | Normally C1-S5, 23 Nov–6 Dec; PYB-008/009/013 and included fixes | Applicable exact-artifact matrix and normative gates pass; provenance/recovery/instructions; no unresolved release-blocking data-loss, unintended/cross-session write, or critical workflow regression within the accepted threat model | SG1: release or submission decision with required sign-off; release owner and QA/review path | |
53 | | -| M-05 — Proposed | Users can obtain the selected qualified app build through a verified existing channel | C1-S5–C1-S6, 23 Nov–20 Dec; PYB-014 and residual 002 | M-04; distribution-owner access; separate submission, availability, installed build/provenance, and installation outcome records; current user-facing claims | Verified-channel milestone passes only for the stated evidence; store delays are recorded as blockers; release owner | |
| 52 | +| M-04 — In progress; admission pending | A frozen maintenance candidate is qualified for its declared release scope | Normally C1-S5, 23 Nov–6 Dec; PYB-008/009/013 and included fixes | Applicable exact-artifact matrix and normative gates pass; provenance/recovery/instructions; no unresolved release-blocking data-loss, unintended/cross-session write, or critical workflow regression within the accepted threat model | SG1: release or submission decision with required sign-off; release owner and QA/review path | |
| 53 | +| M-05 — Preparation in progress; delivery pending | Users can obtain the selected qualified app build through a verified existing channel | C1-S5–C1-S6, 23 Nov–20 Dec; PYB-014 and residual 002 | M-04; distribution-owner access; separate submission, availability, installed build/provenance, and installation outcome records; current user-facing claims | Verified-channel milestone passes only for the stated evidence; store delays are recorded as blockers; release owner | |
54 | 54 | | M-06 — Proposed | Useful-repeat and support evidence drives one explicit next-stage investment | C1-S6, 7–20 Dec; PYB-011 follow-up, cycle review; Ready inputs only if selected | Mature consented cohort accounting, useful Task C/return outcomes, task opportunity, prompting, missing responses, support burden, and status of candidate/channel evidence; retain blocked outcomes | SG3 assessment plus dated continue/narrow/pause-expansion decision; Product Owner with pilot and Developers | |
55 | 55 |
|
56 | 56 | [C1-S1 evidence](c1-s1/00_Execution_Record.md) includes the ledger, pilot protocol, recovery contract, cost model and verified existing Play/TestFlight installations. Six tasks are Done, two are Prepared awaiting pilot setup and four await participant/observation evidence. Human ownership, cohort/setup and actual capacity remain unconfirmed, so M-01/SG0 remains blocked. Missing participants are recorded as a recruitment gap, not completed observations. Current-build verification does not pass M-05 for a future qualified update. M-02's S2–S3 window is the original baseline; a sized S2–S4 option now requires explicit replanning, with downstream matrix/recruitment dates reviewed together. |
|