Next SDAQF Prerelease Release Readiness ExecPlan

Status

PLANNING_PR_MERGED_EXACT_CI_COMPLETE_OWNER_RELEASE_METADATA_PENDING

This is a living ExecPlan under PLANS.md. It plans a possible next SDAQF prerelease after pull request #4; it does not authorize or perform a version change, tag, release, deployment, or repository-setting change.

Objective and measurable completion state

Prepare an evidence-backed readiness path for the next SDAQF prerelease from the post-merge main state while preserving the published v1.0.0-rc.1 release and every historical review and Gate record.

This planning stage is complete when:

  • post-merge current-status documentation states that pull request #4 and its exact pull-request CI completed, and that the resulting main merge commit passed its exact-triggering-SHA CI matrix;
  • release direction, recommended milestone scope, compatibility boundaries, unresolved Owner decisions, future Gates, and stop conditions are explicit;
  • documentation and public-contract tests, Ruff, the necessary strict type check, and git diff --check pass;
  • three independent read-only reviewers ACCEPT the final planning diff with no unresolved Critical, High, or Medium finding; and
  • the planning branch is published only through an explicitly staged English commit, normal push, English draft pull request, and successful exact pull- request CI.

The release-readiness stage remains open after this planning pull request. It cannot complete until the Owner decides every release-metadata item below and a later exact release candidate passes the full candidate-bound Gate sequence.

Starting state and source requirements

  • Repository boundary: repo/ only; the parent workspace is local-only.
  • Baseline branch: main.
  • Baseline commit: a6195e1aafcbcdd288b465cc9d8572df6d4e33ee, the merge commit for pull request #4.
  • Pull request #4 exact head CI: run 31558960113, completed successfully for Windows and Linux on Python 3.12 and 3.13.
  • Post-merge main exact-triggering-SHA CI: run 31563987706, completed successfully for the same four required jobs.
  • Worktree and index: clean before the planning branch was created.
  • Published baseline: distribution version 1.0.0rc1, annotated tag v1.0.0-rc.1, release title SDAQF v1.0.0-rc.1, prerelease true, no attached assets, no package-registry publication, and GitHub-provided source archives.

Repository implementation, tests, schemas, examples, milestone ExecPlans, release contracts, and tracked publication records are the allowed evidence. No credentials, personal data, private workspace reports, external-system investigation, or network diagnostics belong in this plan.

Release direction

The recommended direction is prepare the next prerelease, not release now and not prepare stable 1.0.

M5 through M8 are implemented and independently have current GO dispositions, but they remain Experimental and unreleased. They introduce a large linked public surface after v1.0.0-rc.1, while macOS, independent production deployment, hosted-agent operation, and third-party solver integration remain unverified. A prerelease gives that surface an explicit evaluation boundary before any stable compatibility commitment.

The recommended release scope is M5, M6, M7, and M8 together. M6 consumes M5 identity, M7 reuses M5 and M6 authority, and M8 composes all three. A source archive from current main contains the complete linked implementation, so a notes-only partial scope would not match the delivered source. Excluding a milestone requires a separately designed code candidate and is outside this planning change.

Compatibility boundaries

  • M5 publishes strict context schemas and additive context CLI behavior without widening the stable top-level Python exports.
  • M6 keeps M6-only scheduler schema 1 as the default. M8 requires scheduler schema 2; movement from schema 1 to 2 is explicit, Owner-approved, copy-on-write, and never an automatic in-place migration or downgrade.
  • M7 remains a bounded, exact finite-domain reference solver. Approximate semantics, new result states, or executable external adapters require a new contract decision.
  • M8 preserves existing genesis call shapes and adds predecessor scheduler authority only for successor lineage.
  • Documented CLI behavior, published JSON schemas, and sdaqf.__all__ are the intended public surface. Other Python modules remain prerelease implementation details unless the Owner explicitly broadens that boundary.

The historical M5 and M6 NO-GO records, the later M6 review stop, M8 review caveats, finding severities and counts, past candidate records, and past Gate results remain immutable historical evidence. Current GO dispositions do not rewrite those checkpoints and do not establish release GO or production readiness.

Owner decision register

No row below is implicitly approved by this plan.

ID Decision Recommendation Status
NP-D1 Release direction Prepare another prerelease; do not promote directly to stable 1.0 OWNER_DECISION_REQUIRED
NP-D2 Included scope Include M5 through M8 together OWNER_DECISION_REQUIRED
NP-D3 Distribution version Select a new unused PEP 440 prerelease version in the target 1.0 line; do not assume 1.0.0rc2 OWNER_DECISION_REQUIRED
NP-D4 Git tag Select a new unused tag that maps exactly to the approved version OWNER_DECISION_REQUIRED
NP-D5 Release title Select a title consistent with the approved tag and SDAQF naming OWNER_DECISION_REQUIRED
NP-D6 Release notes Approve a new notes path and content covering M5-M8, compatibility, migrations, limits, evidence, and rollback; do not edit the rc1 notes OWNER_DECISION_REQUIRED
NP-D7 GitHub release flags prerelease: true, latest: false OWNER_DECISION_REQUIRED
NP-D8 Artifact composition GitHub source archives only, no attached assets, and no package-registry publication OWNER_DECISION_REQUIRED
NP-D9 Release QA contract Add a new versioned candidate contract after metadata approval; do not mutate the rc1-literal schema or loader behavior OWNER_DECISION_REQUIRED
NP-D10 Stable 1.0 exit criteria Reassess only after the new prerelease has release-specific evidence and observed feedback OWNER_DECISION_REQUIRED

Before NP-D3 through NP-D5 are approved, confirm only availability and consistency of the proposed version, tag, and title. Availability checking does not reserve or create a tag or release.

Scope of this planning change

This planning change may:

  • add this living ExecPlan;
  • reconcile only current-status statements made stale by pull request #4;
  • update public-contract assertions that protect the reconciled facts; and
  • record validation and independent final-review results in this plan.

It must not:

  • change pyproject.toml, src/sdaqf/__init__.py, runtime code, schemas, examples, evaluation fixtures, or release QA behavior;
  • edit docs/releases/v1.0.0-rc.1.md, the published release, the v1.0.0-rc.1 tag, or rc1-specific metadata and Gate evidence;
  • create a candidate fingerprint or hash list;
  • merge a pull request, select or change a version, create a tag or release, upload an artifact, publish a package, or deploy anything; or
  • rewrite historical NO-GO, review caveat, finding-count, or Gate-result text.

Checkpoints and validation

Checkpoint 0 - post-merge preflight

  • Confirm pull request #4 is merged.
  • Confirm remote main resolves to its merge commit.
  • Confirm exact pull-request CI run 31558960113 passed all four required jobs.
  • Confirm exact post-merge main CI run 31563987706 passed all four required jobs.
  • Confirm the starting worktree and index are clean.

Checkpoint 1 - independent readiness assessment

  • Obtain three independent read-only assessments for M5-M8 scope and compatibility, release metadata and Gates, and historical/document/test consistency.
  • Record the shared recommendation to prepare the next prerelease and the shared rejection of direct stable 1.0 preparation.
  • Identify post-merge current-status drift and the missing next-prerelease living plan as the required planning remediations.

Checkpoint 2 - minimal planning implementation

  • Reconcile the M6 active ExecPlan and current-status documents without altering historical checkpoints.
  • Add public-contract assertions for the post-merge facts and this plan.
  • Confirm the diff does not modify rc1 metadata, notes, release QA, schemas, runtime behavior, or published-release records.
  • Pass 106 focused documentation and public-contract tests, the publication audit, Ruff, strict mypy over 180 source files, and whitespace checks.

Run from the repository root:

python scripts/run_local_gate.py pytest tests/test_public_artifacts.py tests/test_v1_public_contracts.py tests/test_v1_release_readiness.py tests/test_m6_public_contracts.py tests/test_m8_public_contracts.py
python scripts/run_local_gate.py publication
python scripts/run_local_gate.py ruff
python scripts/run_local_gate.py mypy
git diff --check

Checkpoint 3 - final planning review and pull request

  • Obtain three fresh independent read-only final-diff reviews.
  • Require all three reviewers to ACCEPT with zero unresolved Critical, High, or Medium finding.
  • Explicitly stage only the reviewed planning paths, create an English commit, normally push the branch, and open English draft pull request #5.
  • Confirm exact-head run 31586128196 passed all four Windows/Linux and Python 3.12/3.13 jobs, mark pull request #5 ready, and merge it normally.
  • Confirm post-merge main run 31594557932 passed the same four jobs for the exact pull request #5 merge-commit state.

Checkpoint 4 - Owner-approved candidate design

This later checkpoint begins only after NP-D1 through NP-D10 are explicit. Implement the chosen version and metadata as a new candidate. Preserve rc1 contracts and records; add versioned release QA behavior where needed. Add or update release notes, changelog current entries, compatibility guidance, package metadata, and contract tests only inside a separately approved scope.

Checkpoint 5 - exact candidate readiness

Run the complete Release Contract without lowering any threshold: full pytest, coverage, Ruff, strict mypy, M5-M8 named validators, offline CLI smoke, evaluation reproduction, workspace/publication/dependency audits, pip check, and git diff --check. Require a clean exact Git candidate, candidate-bound G1-G4 evidence, three independent ACCEPT reviews, and successful exact-SHA CI for the approved Windows/Linux Python 3.12/3.13 matrix. macOS remains NOT_VERIFIED unless actually observed for that exact candidate.

No fingerprint or hash list is part of this planning work. A later release may refer to its exact Git commit and contract-required evidence only after the Owner approves that candidate workflow.

Checkpoint 6 - separately authorized publication

Tag creation, release creation, flags, notes, artifact upload, package publication, repository settings, and post-publication observation are separate Owner approval boundaries. A failure or ambiguity stops the sequence; no prior success compensates for a failed Gate.

Risks and assumptions

  • The next prerelease exposes M5-M8 for the first time, so compatibility risk is materially higher than the planning-only diff.
  • The current rc1-specific release QA schema and loader intentionally contain rc1 literals. Mutating them would destroy historical contract meaning; additive versioning is required for a new candidate.
  • Source-only delivery is the lowest-complexity artifact recommendation. Any wheel, sdist, package-registry, or attached-asset decision adds build, provenance, installation, checksum, allowlist, and rollback Gates.
  • Exact-SHA CI supports only the commit and matrix observed. It is not evidence for macOS, production deployment, hosted agents, or third-party solvers.
  • The plan assumes no runtime or schema change is needed merely to describe the next candidate. A contrary finding stops this scope and requires a new plan.

Stop conditions

Stop before staging, commit, push, or pull-request creation if any requested Gate fails, any Critical, High, or Medium finding remains, any reviewer does not ACCEPT, or the diff touches an unintended or protected path.

Stop and request Owner direction before any scope, version, tag, title, notes, flag, artifact, compatibility, dependency, license, security-policy, stable-API, or release-QA decision. Also stop before merge, tag, release, deployment, package publication, asset upload, repository-setting change, destructive cleanup, history rewrite, force push, credential access, or paid action.

Technical sandbox handling

Use scripts/run_local_gate.py so caches, bytecode, pytest state, coverage data, and other temporary outputs remain in an owned system-temp fixture and are removed after each command. If a required command is denied by the sandbox, classify the denial before requesting one minimum technical approval for the exact command. A technical approval never replaces an Owner decision or external-action approval.

Language and publication boundaries

Tracked text, branch names, commits, and GitHub-facing metadata are English. No private parent-workspace report or personal information may be copied into the repository. This plan may publish only a draft planning pull request after its Gates; it cannot publish a SDAQF release.

Decision log

  • 2026-08-12: Selected prepare the next prerelease as the evidence-backed recommendation. Direct stable 1.0 preparation is not supported while M5-M8 are Experimental and first-release evidence remains outstanding.
  • 2026-08-12: Recommended M5-M8 as one source candidate because their contracts form a dependency chain and current main delivers them together.
  • 2026-08-12: Kept version, tag, title, notes, GitHub flags, and artifacts as explicit Owner decisions. In particular, no rc2 value is assumed.
  • 2026-08-12: Protected all rc1 metadata, notes, release QA, tags, and published release facts; a future candidate must use additive versioned release QA.

Progress log

  • 2026-08-12: Verified pull request #4 merge, exact pull-request CI, post-merge main exact-SHA CI, and a clean starting worktree.
  • 2026-08-12: Three independent read-only assessments found no Critical or High blocker. They converged on the next-prerelease recommendation and identified the same post-merge documentation drift; the document/test reviewer also identified the absence of this living plan.
  • 2026-08-12: Added this plan, reconciled only the post-merge current-status boundary, added focused public-contract assertions, and confirmed that no rc1 metadata, notes, release QA, schema, runtime, or published-release path is in the diff.
  • 2026-08-12: Passed 106 focused tests, the publication audit, Ruff, strict mypy over 180 source files, tracked git diff --check, and the equivalent no-index whitespace check for this then-untracked plan.
  • 2026-08-12: Three independent read-only final-diff reviewers each returned ACCEPT. No reviewer reported a finding, and unresolved Critical, High, and Medium findings are zero.
  • 2026-08-12: Published the reviewed planning commit through draft pull request #5. Exact-head run 31586128196 passed all four required jobs, pull request #5 was marked ready and merged normally, and post-merge main run 31594557932 passed the same exact-state matrix. No version, tag, Release, artifact publication, or deployment was performed or authorized.