name lot-sizing
description When the user wants to model and solve dynamic lot-sizing problems, from uncapacitated single-item lot sizing to multi-item capacitated lot sizing (CLSP) with setup times, covering Wagner-Whitin DP, facility-location reformulation, (l,S) valid inequalities, big-bucket vs small-bucket models, and fix-and-optimize. Also use when the user mentions "lot sizing," "Wagner-Whitin," "setup costs," "CLSP," "production planning periods," or a setup-vs-holding cost trade-off over a discrete horizon. For DP recursion design, see dynamic-programming; for MIP-based improvement loops, see matheuristics.

Lot Sizing

You are an expert in dynamic lot-sizing models for production planning. This skill covers the uncapacitated single-item problem (ULS) solved exactly by the Wagner-Whitin dynamic program, the multi-item capacitated lot-sizing problem (CLSP) with setup costs and setup times, strong reformulations (facility-location, (l,S) valid inequalities), the big-bucket vs small-bucket model families, and fix-and-optimize matheuristics for large instances. Use the framework below to classify the variant, pick the right formulation strength, and deliver a validated production plan with a defensible optimality gap.

Initial Assessment

Establish these facts before formulating anything:

  • Capacity. Is per-period production capacity binding? Uncapacitated single-item problems are polynomially solvable; capacity makes even the single-item case NP-hard.
  • Number of items and periods. N items × T periods sets the binary count (N·T setup variables). N·T ≤ a few thousand is comfortable MIP territory; beyond that plan for matheuristics.
  • Bucket size. Are periods long (weeks/months, many setups per period — big bucket) or short (shifts/hours, at most one or two products per period — small bucket)? This decides the model family before any code is written.
  • Setup structure. Setup costs only, or also setup times that consume capacity? Setup times change the complexity class of the feasibility question. Ask about setup carryover across periods and sequence-dependent setups.
  • Cost structure. Time-varying or constant setup/holding/production costs? Constant unit production cost can be dropped from the objective (total production equals total demand when backlog is forbidden).
  • Backlogging and lost sales. Hard demand satisfaction, backlog at a cost, or lost sales? This changes the flow-balance constraints and the validity of zero-inventory-ordering arguments.
  • Lot-size restrictions. Minimum lot sizes, batch multiples, or all-or-nothing production invalidate the Wagner-Whitin structure and need extra integer variables.
  • Demand certainty. Deterministic forecast, or stochastic demand needing safety stock / scenario models? A deterministic model re-solved in a rolling horizon is the common practical pattern.
  • Horizon usage. One-shot plan or rolling horizon? Rolling horizons need end-of-horizon inventory rules and frozen periods to control nervousness.
  • Quality requirement and time budget. Proven optimality (MIP with strong formulation), small gap in minutes (matheuristic), or instant answer (DP / construction heuristic)?
  • Solver availability. Gurobi license, or open-source only? The DP and the metaheuristic below need only numpy; the MIP sections need a MILP solver.
  • Data format. Demand matrix orientation (items × periods), units of capacity (hours vs pieces), and whether quantities must be integral (usually production quantities may stay continuous).

Problem Variants and Formulations

Notation

Items $i = 1,\dots,N$; periods $t = 1,\dots,T$. Data: demand $d_{it} \ge 0$, setup cost $f_i$, holding cost $h_i$ per unit per period, processing time $a_i$ capacity units per unit, setup time $st_i$, capacity $C_t$. Variables: production $x_{it} \ge 0$, end-of-period inventory $s_{it} \ge 0$ (with $s_{i0} = 0$), setup indicator $y_{it} \in {0,1}$.

ULS — uncapacitated single-item lot sizing

$$ \min \sum_{t=1}^{T} \big( f_t, y_t + h_t, s_t \big) \quad \text{s.t.} \quad s_{t-1} + x_t = d_t + s_t,\qquad x_t \le \Big(\sum_{u=t}^{T} d_u\Big), y_t,\qquad x_t, s_t \ge 0,; y_t \in {0,1}. $$

Zero-inventory ordering (ZIO). Wagner & Whitin (1958) proved an optimal solution exists with $s_{t-1}, x_t = 0$ for all $t$: you never produce while still holding stock. So each demand $d_u$ is produced entirely in one period $t \le u$, and the horizon splits into regeneration intervals. This yields an $O(T^2)$ dynamic program; refinements reach $O(T \log T)$ (Federgruen & Tzur 1991; Wagelmans, van Hoesel & Kolen 1992; Aggarwal & Park 1993). ULS is the textbook entry point of dynamic-programming for planning problems.

CLSP — capacitated multi-item, big bucket

$$ \min \sum_{i=1}^{N}\sum_{t=1}^{T} \big( f_i, y_{it} + h_i, s_{it} \big) $$

$$ s_{i,t-1} + x_{it} = d_{it} + s_{it} ;;\forall i,t; \qquad \sum_{i=1}^{N} \big( a_i, x_{it} + st_i, y_{it} \big) \le C_t ;;\forall t; \qquad x_{it} \le M_{it}, y_{it} ;;\forall i,t, $$

with the tightest valid big-M $M_{it} = \min\big( \sum_{u \ge t} d_{iu},; (C_t - st_i)/a_i \big)$.

Complexity. Single-item lot sizing with general time-varying capacities is NP-hard (Florian, Lenstra & Rinnooy Kan 1980; Bitran & Yanasse 1982); with constant capacity and integer data it admits an $O(T^4)$ DP (Florian & Klein 1971). For the multi-item CLSP with positive setup times, even deciding feasibility is NP-complete (Maes, McClain & Van Wassenhove 1991) — that is why practical codes add overtime variables.

Big-bucket vs small-bucket model families

Model Bucket Per-period structure Sequencing Key reference
CLSP big many items, one setup each none inside period Trigeiro, Thomas & McClain (1989)
CLSPL big CLSP + setup carryover between periods first/last item only Suerie & Stadtler (2003)
DLSP small ≤1 item, all-or-nothing at full capacity implicit Fleischmann (1990)
CSLP small ≤1 item, any quantity up to capacity implicit Karmarkar & Schrage (1985)
PLSP small ≤1 setup change, so up to 2 items implicit Drexl & Haase (1995)
GLSP hybrid macro-period capacity, micro-period sequence full Fleischmann & Meyr (1997)

Use big-bucket models when periods are weeks or months and shop-floor sequencing is decided downstream. Switch to small-bucket or GLSP models when setups carry over between short periods or are sequence-dependent — there, lot sizing and scheduling cannot be separated.

Strong reformulations

The big-M linking constraint makes the standard LP relaxation notoriously weak. Two classical repairs, both from the single-item polyhedron, also tighten every item's substructure inside the CLSP (Pochet & Wolsey 2006, Production Planning by Mixed Integer Programming):

Facility-location reformulation (Krarup & Bilde 1977). Disaggregate production: $w_{itu}$ = quantity produced in period $t$ to serve demand $d_{iu}$, $t \le u$:

$$ \min \sum_{i,t} f_i, y_{it} + \sum_{i,, t \le u} h_i (u-t), w_{itu} \quad \text{s.t.} \quad \sum_{t \le u} w_{itu} = d_{iu} ;;\forall i,u; \qquad w_{itu} \le d_{iu}, y_{it}. $$

For uncapacitated single-item instances, its LP relaxation has an integral optimal $y$ — it describes the convex hull. Cost: $O(N T^2 / 2)$ variables.

(l,S) valid inequalities (Barany, Van Roy & Wolsey 1984). For each $l \in {1,\dots,T}$ and each $S \subseteq {1,\dots,l}$:

$$ \sum_{t \in S} x_t ;\le; s_l + \sum_{t \in S} d_{t,l}; y_t, \qquad d_{t,l} = \sum_{u=t}^{l} d_u . $$

Together with the trivial inequalities these give the full convex hull of ULS solutions. There are exponentially many, but exact separation is $O(T^2)$ per item: given an LP point $(x^, y^, s^)$, the most violated set is $S^ = { t \le l : x^t > d{t,l}, y^_t }$. So the small standard model plus a cut loop reaches the same bound as the large FL model.

Method selection

Situation Method
Single item, no capacity Wagner-Whitin DP, exact in $O(T^2)$
Single item, constant capacity, integer data Florian-Klein DP, $O(T^4)$
CLSP, up to a few thousand setup binaries MIP with FL reformulation or (l,S) cut loop
Large CLSP, setup times, overtime fix-and-optimize / relax-and-fix (see matheuristics)
Setup carryover or sequence-dependent setups CLSPL / GLSP models, metaheuristics
Stochastic demand static-dynamic strategies, two-stage scenario models

Instance Generation and Validation

Build these two functions first: every later section reuses the instance container and reports through the independent validator. The generator follows the design of the classic Trigeiro, Thomas & McClain (1989) CLSP test bed: setup costs are derived from a target time-between-orders (TBO) via the EOQ relation $TBO = \sqrt{2 f / (h \bar d)}$, and capacity is set from a target utilization.

from dataclasses import dataclass

import numpy as np


@dataclass(frozen=True)
class ClspInstance:
    """Multi-item big-bucket CLSP data. Shapes: demand (N, T); item arrays (N,); capacity (T,)."""
    demand: np.ndarray        # d[i, t] >= 0
    setup_cost: np.ndarray    # f[i]
    holding_cost: np.ndarray  # h[i] per unit per period
    prod_time: np.ndarray     # a[i] capacity units per produced unit
    setup_time: np.ndarray    # st[i] capacity units per setup
    capacity: np.ndarray      # C[t]


def generate_clsp_instance(n_items: int, n_periods: int, seed: int,
                           tbo: float = 2.0, utilization: float = 0.85,
                           demand_cv: float = 0.35) -> ClspInstance:
    """Trigeiro-style CLSP generator: TBO sets setup costs, utilization sets capacity tightness."""
    rng = np.random.default_rng(seed)
    mean_demand = rng.uniform(50.0, 150.0, n_items)
    demand = rng.normal(mean_demand[:, None], demand_cv * mean_demand[:, None],
                        (n_items, n_periods))
    demand = np.clip(np.rint(demand), 0.0, None)
    holding_cost = rng.uniform(0.5, 1.5, n_items)
    setup_cost = 0.5 * tbo ** 2 * holding_cost * demand.mean(axis=1)  # EOQ-derived
    prod_time = np.ones(n_items)
    setup_time = rng.uniform(10.0, 50.0, n_items)
    mean_load = (prod_time[:, None] * demand).sum(axis=0).mean()
    capacity_value = (mean_load + setup_time.sum() / tbo) / utilization
    capacity = np.full(n_periods, capacity_value)
    return ClspInstance(demand, setup_cost, holding_cost, prod_time, setup_time, capacity)


inst = generate_clsp_instance(n_items=4, n_periods=8, seed=42)
print(inst.demand.shape, float(inst.demand.sum()), round(float(inst.capacity[0]), 1))
# Expected: (4, 8) 3870.0 646.4 — identical numbers on every rerun with seed 42.

Raise utilization toward 1.0 and tbo above 3 to create hard instances; setup-time-heavy, tightly capacitated instances are the hardest in the Trigeiro set. The validator below recomputes everything from raw data — never trust the model's own bookkeeping when reporting results:

import numpy as np


def validate_clsp_solution(inst: ClspInstance, x: np.ndarray, y: np.ndarray,
                           tol: float = 1e-6) -> tuple[bool, float, list[str]]:
    """Independent feasibility check and objective recomputation; no solver objects involved."""
    violations: list[str] = []
    inventory = np.cumsum(x - inst.demand, axis=1)
    if (x < -tol).any():
        violations.append("negative production quantity")
    if (inventory < -tol).any():
        i, t = map(int, np.argwhere(inventory < -tol)[0])
        violations.append(f"unmet demand: item {i}, period {t}")
    if ((x > tol) & (y < 0.5)).any():
        i, t = map(int, np.argwhere((x > tol) & (y < 0.5))[0])
        violations.append(f"production without setup: item {i}, period {t}")
    load = (inst.prod_time[:, None] * x + inst.setup_time[:, None] * y).sum(axis=0)
    if (load > inst.capacity + tol).any():
        t = int(np.argwhere(load > inst.capacity + tol)[0][0])
        violations.append(f"capacity exceeded in period {t}")
    objective = float((inst.setup_cost[:, None] * y).sum()
                      + (inst.holding_cost[:, None] * np.clip(inventory, 0.0, None)).sum())
    return (not violations, objective, violations)


inst = generate_clsp_instance(n_items=4, n_periods=8, seed=42)
x_lfl = inst.demand.astype(float)              # lot-for-lot plan
y_lfl = (inst.demand > 0).astype(float)
ok, obj, viol = validate_clsp_solution(inst, x_lfl, y_lfl)
print(ok, round(obj, 1), viol)
# Expected: False 6802.5 ['capacity exceeded in period 2'] — lot-for-lot pays a setup
# for every item in every period, and the setup hours overload the tight periods.

Wagner-Whitin Dynamic Program

The exact ULS solver. State: $F(t)$ = minimum cost of satisfying demands $1..t$, with $F(0) = 0$. By ZIO, the last regeneration interval is produced entirely in some period $j$:

$$ F(t) = \min_{1 \le j \le t} \Big{ F(j-1) + f_j + \sum_{u=j}^{t} \Big( \sum_{v=j}^{u-1} h_v \Big) d_u \Big}. $$

Prefix sums make each candidate cost $O(1)$, so the whole DP is $O(T^2)$ — instant for any practical horizon. The implementation supports time-varying setup and holding costs and skips the setup charge on zero-demand intervals:

import numpy as np


def wagner_whitin(demand: np.ndarray, setup_cost: np.ndarray,
                  holding_cost: np.ndarray) -> tuple[float, list[int]]:
    """O(T^2) DP for single-item uncapacitated lot sizing (Wagner & Whitin 1958).

    Returns (optimal cost, 0-indexed setup periods). Supports time-varying f_t, h_t.
    """
    T = len(demand)
    cum_h = np.concatenate(([0.0], np.cumsum(holding_cost)))        # sum h[0..t-1]
    cum_d = np.concatenate(([0.0], np.cumsum(demand)))
    cum_hd = np.concatenate(([0.0], np.cumsum(cum_h[:T] * demand)))
    F = np.full(T + 1, np.inf)
    F[0] = 0.0
    pred = np.zeros(T + 1, dtype=int)
    for t in range(T):
        j = np.arange(t + 1)
        interval_demand = cum_d[t + 1] - cum_d[j]
        produce_cost = setup_cost[j] + (cum_hd[t + 1] - cum_hd[j]) - cum_h[j] * interval_demand
        produce_cost = np.where(interval_demand > 0, produce_cost, 0.0)  # no demand, no setup
        total = F[j] + produce_cost
        k = int(np.argmin(total))
        F[t + 1] = total[k]
        pred[t + 1] = k
    setups, t = [], T
    while t > 0:
        j = pred[t]
        if cum_d[t] - cum_d[j] > 0:
            setups.append(int(j))
        t = j
    return float(F[T]), setups[::-1]


cost, setups = wagner_whitin(np.array([10.0, 20.0, 30.0]),
                             np.array([40.0, 40.0, 40.0]),
                             np.array([1.0, 1.0, 1.0]))
print(cost, setups)
# Expected: 100.0 [0, 2] — produce 30 units in period 0 (holding d_2 one period costs 20)
# and 30 units in period 2; all four ZIO plans cost 120/110/100/120.

Use Wagner-Whitin three ways inside capacitated work: as the exact solver when capacity never binds, as a per-item lower-bounding and seeding device (solve each item alone, ignore capacity), and as the subproblem inside Lagrangian or column-generation schemes for the CLSP. The $O(T \log T)$ refinements matter only when ULS is called millions of times inside such loops. For deeper recursion-design guidance see dynamic-programming.

Exact MIP Models in gurobipy

Standard CLSP with constraint-builder functions

Each constraint family lives in its own builder so it can be unit-tested and reused by the reformulation and the matheuristic. Note model.update() at the end of the builder: gurobipy's lazy updates otherwise leave relax() and getVars() looking at an empty model.

import gurobipy as gp
import numpy as np
from gurobipy import GRB


def add_flow_balance_constraints(model: gp.Model, v: dict, data: ClspInstance) -> None:
    """Inventory balance s[i,t-1] + x[i,t] == d[i,t] + s[i,t], with s[i,-1] = 0."""
    N, T = data.demand.shape
    x, s = v["x"], v["s"]
    for i in range(N):
        for t in range(T):
            prev = s[i, t - 1] if t > 0 else 0.0
            model.addConstr(prev + x[i, t] == data.demand[i, t] + s[i, t],
                            name=f"flow[{i},{t}]")


def add_setup_linking_constraints(model: gp.Model, v: dict, data: ClspInstance) -> None:
    """x[i,t] <= M[i,t] y[i,t] with the tightest valid big-M (remaining demand vs capacity)."""
    N, T = data.demand.shape
    x, y = v["x"], v["y"]
    remaining = data.demand[:, ::-1].cumsum(axis=1)[:, ::-1]
    for i in range(N):
        for t in range(T):
            cap_bound = (data.capacity[t] - data.setup_time[i]) / data.prod_time[i]
            big_m = min(remaining[i, t], max(cap_bound, 0.0))
            model.addConstr(x[i, t] <= big_m * y[i, t], name=f"link[{i},{t}]")


def add_capacity_constraints(model: gp.Model, v: dict, data: ClspInstance) -> None:
    """Production plus setup time within period capacity: sum_i a_i x[i,t] + st_i y[i,t] <= C_t."""
    N, T = data.demand.shape
    x, y = v["x"], v["y"]
    for t in range(T):
        model.addConstr(
            gp.quicksum(data.prod_time[i] * x[i, t] + data.setup_time[i] * y[i, t]
                        for i in range(N)) <= data.capacity[t],
            name=f"cap[{t}]")


def build_clsp_model(data: ClspInstance) -> tuple[gp.Model, dict]:
    """Standard inventory-and-setup CLSP MIP."""
    N, T = data.demand.shape
    model = gp.Model("clsp")
    model.Params.OutputFlag = 0
    v = {"x": model.addVars(N, T, lb=0.0, name="x"),
         "s": model.addVars(N, T, lb=0.0, name="s"),
         "y": model.addVars(N, T, vtype=GRB.BINARY, name="y")}
    add_flow_balance_constraints(model, v, data)
    add_setup_linking_constraints(model, v, data)
    add_capacity_constraints(model, v, data)
    model.setObjective(
        gp.quicksum(data.setup_cost[i] * v["y"][i, t] + data.holding_cost[i] * v["s"][i, t]
                    for i in range(N) for t in range(T)),
        GRB.MINIMIZE)
    model.update()
    return model, v


def solve_clsp(data: ClspInstance, time_limit: float = 60.0) -> tuple[float, np.ndarray, np.ndarray]:
    """Solve the CLSP and return (objective, production matrix, setup matrix)."""
    model, v = build_clsp_model(data)
    model.Params.TimeLimit = time_limit
    model.Params.MIPGap = 1e-6
    model.optimize()
    assert model.Status == GRB.OPTIMAL or (model.Status == GRB.TIME_LIMIT and model.SolCount > 0)
    N, T = data.demand.shape
    x = np.array([[v["x"][i, t].X for t in range(T)] for i in range(N)])
    y = np.array([[round(v["y"][i, t].X) for t in range(T)] for i in range(N)])
    return model.ObjVal, x, y


inst = generate_clsp_instance(n_items=4, n_periods=8, seed=42)
obj_mip, x_mip, y_mip = solve_clsp(inst)
print(round(obj_mip, 1), validate_clsp_solution(inst, x_mip, y_mip)[:2])
# Expected: 5571.5 (True, 5571.501...) — optimal in well under a second; the independent
# validator reproduces the solver objective exactly.

For general gurobipy patterns (parameters, statuses, infeasibility diagnosis) see milp-modeling-gurobi.

Facility-location reformulation

Same optimum, far stronger LP relaxation. The price is $O(N T^2/2)$ w variables — worth paying up to horizons of 50-100 periods. The holding coefficient $h_i(u-t)$ assumes item-constant holding cost; with time-varying $h_{it}$ replace it by the cumulative sum between $t$ and $u$.

import gurobipy as gp
import numpy as np
from gurobipy import GRB


def build_clsp_fl_model(data: ClspInstance) -> tuple[gp.Model, dict]:
    """Facility-location reformulation (Krarup & Bilde 1977): w[i,t,u] serves demand (i,u) from t."""
    N, T = data.demand.shape
    model = gp.Model("clsp_fl")
    model.Params.OutputFlag = 0
    triples = [(i, t, u) for i in range(N) for u in range(T)
               if data.demand[i, u] > 0 for t in range(u + 1)]
    w = model.addVars(triples, lb=0.0, name="w")
    y = model.addVars(N, T, vtype=GRB.BINARY, name="y")
    for i in range(N):
        for u in range(T):
            if data.demand[i, u] > 0:
                model.addConstr(gp.quicksum(w[i, t, u] for t in range(u + 1))
                                == data.demand[i, u], name=f"demand[{i},{u}]")
    for (i, t, u) in triples:
        model.addConstr(w[i, t, u] <= data.demand[i, u] * y[i, t], name=f"open[{i},{t},{u}]")
    by_period: dict[int, list[tuple[int, int]]] = {t: [] for t in range(T)}
    for (i, t, u) in triples:
        by_period[t].append((i, u))
    for t in range(T):
        model.addConstr(
            gp.quicksum(data.prod_time[i] * w[i, t, u] for (i, u) in by_period[t])
            + gp.quicksum(data.setup_time[i] * y[i, t] for i in range(N))
            <= data.capacity[t], name=f"cap[{t}]")
    model.setObjective(
        gp.quicksum(data.setup_cost[i] * y[i, t] for i in range(N) for t in range(T))
        + gp.quicksum(data.holding_cost[i] * (u - t) * w[i, t, u] for (i, t, u) in triples),
        GRB.MINIMIZE)
    model.update()
    return model, {"w": w, "y": y}


def lp_bound(model: gp.Model) -> float:
    """LP-relaxation bound of a built MIP model."""
    relaxed = model.relax()
    relaxed.Params.OutputFlag = 0
    relaxed.optimize()
    assert relaxed.Status == GRB.OPTIMAL
    return relaxed.ObjVal


inst = generate_clsp_instance(n_items=4, n_periods=8, seed=42)
m_std, _ = build_clsp_model(inst)
m_fl, _ = build_clsp_fl_model(inst)
print(round(lp_bound(m_std), 1), round(lp_bound(m_fl), 1))
# Expected: 2414.6 5397.3 — the standard LP bound is 57% below the MIP optimum 5571.5,
# the FL relaxation closes about 94% of that gap. The FL MIP optimum is also 5571.5.

(l,S) valid inequalities with exact separation

The same bound as the FL model, obtained on the small standard model by a cutting-plane loop. separate_ls_inequalities is the exact $O(N T^2)$ separation; the loop strengthens the root LP. Inside a branch-and-bound run you would add the same cuts through a user-cut callback — the callback machinery is covered in cutting-planes-valid-inequalities.

import gurobipy as gp
import numpy as np
from gurobipy import GRB


def separate_ls_inequalities(data: ClspInstance, x_val: np.ndarray, y_val: np.ndarray,
                             s_val: np.ndarray, eps: float = 1e-4) -> list[tuple[int, int, list[int]]]:
    """Exact separation of (l,S) inequalities (Barany, Van Roy & Wolsey 1984).

    For each item i and end period l, the most violated set is
    S* = {t <= l : x*[t] > d[t..l] * y*[t]}. Returns violated (i, l, S*) triples.
    """
    cuts = []
    N, T = data.demand.shape
    for i in range(N):
        for l in range(T):
            d_tl = np.cumsum(data.demand[i, :l + 1][::-1])[::-1]   # d_tl[t] = d[i, t..l]
            margin = x_val[i, :l + 1] - d_tl * y_val[i, :l + 1]
            S = np.nonzero(margin > eps)[0]
            if margin[S].sum() - s_val[i, l] > eps:
                cuts.append((i, l, S.tolist()))
    return cuts


def clsp_root_cut_loop(data: ClspInstance, max_rounds: int = 50) -> tuple[float, float, int]:
    """Strengthen the root LP with (l,S) cuts; returns (lp_before, lp_after, n_cuts)."""
    model, v = build_clsp_model(data)
    for var in model.getVars():
        var.VType = GRB.CONTINUOUS          # binaries keep their [0,1] bounds
    model.optimize()
    lp0 = model.ObjVal
    N, T = data.demand.shape
    n_cuts = 0
    for _ in range(max_rounds):
        x_val = np.array([[v["x"][i, t].X for t in range(T)] for i in range(N)])
        y_val = np.array([[v["y"][i, t].X for t in range(T)] for i in range(N)])
        s_val = np.array([[v["s"][i, t].X for t in range(T)] for i in range(N)])
        cuts = separate_ls_inequalities(data, x_val, y_val, s_val)
        if not cuts:
            break
        for (i, l, S) in cuts:
            d_tl = np.cumsum(data.demand[i, :l + 1][::-1])[::-1]
            model.addConstr(
                gp.quicksum(v["x"][i, t] for t in S)
                <= v["s"][i, l] + gp.quicksum(d_tl[t] * v["y"][i, t] for t in S),
                name=f"ls[{i},{l},{n_cuts}]")
            n_cuts += 1
        model.optimize()
    return lp0, model.ObjVal, n_cuts


inst = generate_clsp_instance(n_items=4, n_periods=8, seed=42)
lp0, lp_cut, n_cuts = clsp_root_cut_loop(inst)
print(round(lp0, 1), round(lp_cut, 1), n_cuts)
# Expected: 2414.6 5397.3 93 — 93 cuts close 94.5% of the LP gap and reach exactly the
# FL-reformulation bound, as the convex-hull theory predicts.

The residual 5397.3 → 5571.5 gap comes from the capacity coupling between items — no single-item polyhedral result can close it. That part is left to branching.

Metaheuristic: Setup-Pattern GA with ZIO Decoder

For instances beyond MIP reach (hundreds of items, long horizons), search over the binary setup patterns only and let a decoder set the quantities. Given a setup pattern, ZIO assigns every demand to the most recent open setup — optimal per item up to capacity, which is handled by a penalty. The whole population decodes in a few vectorized numpy operations; one well-matched method is enough here, and operator variants (selection, crossover, mutation-rate control) are covered in genetic-algorithms.

import numpy as np


def decode_zio(setups: np.ndarray, data: ClspInstance,
               penalty: float) -> tuple[np.ndarray, np.ndarray, np.ndarray]:
    """Vectorized ZIO decoder: setup patterns (P,N,T) -> plans, effective setups, fitness."""
    P, N, T = setups.shape
    d = data.demand
    first = np.argmax(d > 0, axis=1)                     # earliest positive demand per item
    Y = setups.astype(bool).copy()
    Y[:, np.arange(N), first] = True                     # repair: earliest demand is covered
    src = np.maximum.accumulate(np.where(Y, np.arange(T), -1), axis=2)
    flat_src = np.where(d > 0, src, 0).reshape(P * N, T)  # safe index where demand is zero
    qty = np.broadcast_to(np.where(d > 0, d, 0.0), (P, N, T)).reshape(P * N, T)
    x = np.zeros((P * N, T))
    np.add.at(x, (np.arange(P * N)[:, None], flat_src), qty)
    x = x.reshape(P, N, T)
    y_eff = x > 1e-9                                     # drop setups that produce nothing
    inv = np.cumsum(x - d, axis=2)                       # >= 0 by construction
    cost = (data.setup_cost[None, :, None] * y_eff).sum(axis=(1, 2)) \
        + (data.holding_cost[None, :, None] * inv).sum(axis=(1, 2))
    load = (data.prod_time[None, :, None] * x
            + data.setup_time[None, :, None] * y_eff).sum(axis=1)
    overload = np.clip(load - data.capacity[None, :], 0.0, None).sum(axis=1)
    return x, y_eff.astype(float), cost + penalty * overload


def ga_clsp(data: ClspInstance, pop_size: int = 200, generations: int = 300,
            setup_prob: float = 0.5, mut_rate: float = 0.02, penalty: float = 100.0,
            elite_frac: float = 0.1, seed: int = 0) -> tuple[float, np.ndarray, np.ndarray]:
    """Binary GA over setup patterns; ZIO decoder sets quantities, penalty handles capacity."""
    rng = np.random.default_rng(seed)
    N, T = data.demand.shape
    pop = rng.random((pop_size, N, T)) < setup_prob
    n_elite = max(1, int(elite_frac * pop_size))
    n_child = pop_size - n_elite
    best_fit, best_x, best_y = np.inf, None, None
    for _ in range(generations):
        x, y, fit = decode_zio(pop, data, penalty)
        order = np.argsort(fit)
        if fit[order[0]] < best_fit:
            b = order[0]
            best_fit, best_x, best_y = float(fit[b]), x[b].copy(), y[b].copy()
        cand = rng.integers(0, pop_size, (2, 2 * n_child))        # size-2 tournaments
        winners = np.where(fit[cand[0]] <= fit[cand[1]], cand[0], cand[1])
        pa, pb = winners[:n_child], winners[n_child:]
        mask = rng.random((n_child, N, T)) < 0.5                  # uniform crossover
        children = np.where(mask, pop[pa], pop[pb])
        children ^= rng.random((n_child, N, T)) < mut_rate        # bit-flip mutation
        pop = np.concatenate([pop[order[:n_elite]], children])
    return best_fit, best_x, best_y


inst = generate_clsp_instance(n_items=4, n_periods=8, seed=42)
ga_fit, ga_x, ga_y = ga_clsp(inst, seed=3)
ok, ga_obj, viol = validate_clsp_solution(inst, ga_x, ga_y)
print(round(ga_fit, 1), ok, viol)
# Expected: 5657.4 True [] — capacity-feasible (zero penalty active) and 1.54% above
# the MIP optimum 5571.5; a few seconds for 200 x 300 decoded individuals.

Set setup_prob near 1/tbo so the initial population starts at sensible setup densities, and scale penalty so one unit of overload costs more than the largest setup saving (here capacity units are comparable to holding-cost units, so 100 is safely dominant). If the best individual still carries overload, the validator will say so — report that, never silently accept it.

Advanced Techniques

Fix-and-optimize

The standard matheuristic for large lot-sizing models (Helber & Sahling 2010): keep the full MIP, but free only the setup binaries inside a sliding time window and fix the rest to the incumbent. Each subproblem is small and solves in seconds; the incumbent is always feasible for the next window, so the objective decreases monotonically. Start it from any feasible setup matrix — the GA result is a good seed.

import gurobipy as gp
import numpy as np
from gurobipy import GRB


def fix_and_optimize(data: ClspInstance, y_start: np.ndarray, window: int = 4, step: int = 2,
                     mip_seconds: float = 5.0, passes: int = 2) -> tuple[float, np.ndarray, np.ndarray]:
    """Time-window fix-and-optimize (Helber & Sahling 2010). y_start must be capacity-feasible."""
    model, v = build_clsp_model(data)
    model.Params.TimeLimit = mip_seconds
    N, T = data.demand.shape
    y_inc = np.rint(y_start).astype(float)
    best = np.inf
    for _ in range(passes):
        for w0 in range(0, T, step):
            w1 = min(w0 + window, T)
            for i in range(N):
                for t in range(T):
                    free = w0 <= t < w1
                    v["y"][i, t].LB = 0.0 if free else y_inc[i, t]
                    v["y"][i, t].UB = 1.0 if free else y_inc[i, t]
            model.optimize()
            if model.SolCount > 0 and model.ObjVal < best - 1e-9:
                best = model.ObjVal
                y_inc = np.array([[round(v["y"][i, t].X) for t in range(T)]
                                  for i in range(N)], dtype=float)
    for i in range(N):                       # recover x under the final setup pattern
        for t in range(T):
            v["y"][i, t].LB = y_inc[i, t]
            v["y"][i, t].UB = y_inc[i, t]
    model.optimize()
    x = np.array([[v["x"][i, t].X for t in range(T)] for i in range(N)])
    return model.ObjVal, x, y_inc


inst = generate_clsp_instance(n_items=4, n_periods=8, seed=42)
_, _, y_seed = ga_clsp(inst, seed=3)
fo_obj, fo_x, fo_y = fix_and_optimize(inst, y_seed)
print(round(fo_obj, 1), validate_clsp_solution(inst, fo_x, fo_y)[0])
# Expected: 5571.5 True — fix-and-optimize repairs the 1.54% GA gap to the exact optimum.
# On a 10-item, 12-period instance (seed 1) the same pipeline gives GA 22830.9 ->
# fix-and-optimize 22232.2 vs MIP optimum 22210.0 (0.1% gap).

Window decompositions other than time work too: free all periods of an item subset, or all binaries of one resource. Rotate decompositions when a pass stops improving. Variants, acceptance rules, and budgeting of the inner MIP calls are treated in matheuristics.

Relax-and-fix construction

When no feasible start exists, build one forward in time: in iteration $k$, keep the binaries of window $k$ integral, fix the already-decided earlier windows, and relax all later binaries to $[0,1]$. The relaxed tail approximates future setup costs well because the per-item polyhedron is tight there if you use the FL or (l,S)-strengthened model. With positive setup times, add overtime variables with a high cost so every iteration stays feasible; drive overtime to zero in a second fix-and-optimize phase.

Setup carryover and small-bucket refinements

CLSPL adds binary carryover variables $z_{it}$ ("the machine is still configured for $i$ when period $t$ starts"), with constraints $z_{it} \le y_{i,t-1} + z_{i,t-1}$, $\sum_i z_{it} \le 1$, and a relaxed linking constraint $x_{it} \le M_{it}(y_{it} + z_{it})$ (Suerie & Stadtler 2003 give a tight formulation). Carryover typically saves 3-10% setup time in tightly loaded plans. If setups are sequence-dependent inside periods, move to GLSP-style micro-period models — at that point lot sizing has become lot sizing and scheduling, and metaheuristics or decomposition take over from monolithic MIP.

Rolling horizons and end-of-horizon control

Production plans are re-solved every period with a shifted window. Two standing problems: the model drains inventory to zero at the horizon end (underproduction late in the window), and re-planning flips earlier decisions (nervousness). Standard fixes: impose terminal inventory lower bounds or a salvage value on $s_{iT}$, freeze the first 1-3 periods of each re-plan, and overlap windows so only frozen decisions are executed. Evaluate a rolling policy by simulation over the full demand realization, not by the single-window objective.

Stochastic demand

Under demand uncertainty, classify the policy first (Bookbinder & Tan 1988): static (setup periods and quantities fixed now), static-dynamic (setup periods fixed, quantities decided as demand reveals — the practical favorite, since plan stability is preserved), or dynamic (everything recourse). The static-dynamic strategy becomes a two-stage program: first-stage $y$, second-stage quantities per scenario, solvable in extensive form for moderate scenario counts. Scenario generation, sample-average approximation, and L-shaped decomposition for larger trees are covered in stochastic-optimization.

Practical Challenges

The MIP gap stalls because the LP relaxation is far below any feasible cost. The big-M linking constraints are the cause; on the demo instance the standard LP bound is 57% below the optimum. Use the tightest $M_{it}$ (remaining demand capped by capacity), then either switch to the facility-location reformulation or run an (l,S) cut loop — both closed ~94% of the gap above. Only then increase solver effort.

The solver reports infeasible as soon as setup times are included. Feasibility with setup times is NP-complete (Maes, McClain & Van Wassenhove 1991), and real data is often genuinely overloaded in peak periods. Add overtime variables $o_t$ to the capacity constraints with an explicit, documented cost; a plan that says "12 overtime hours in period 7" is more useful than GRB.INFEASIBLE.

Wagner-Whitin output is used as the production plan although capacity binds. ZIO plans concentrate production and routinely violate tight capacities. Use WW per item only as a seed or bound; let the CLSP model or the fix-and-optimize loop produce the executable plan, and always run the independent validator on whatever is shipped.

Minimum lot sizes or batch multiples quietly invalidate the model. ZIO and the (l,S) hull arguments assume freely divisible lots. Model minimum lots as $x_{it} \ge L_i y_{it}$ (this alone keeps the structure), batch multiples with integer batch-count variables $x_{it} = B_i q_{it}$ — and stop using the WW DP as an exact oracle in either case.

Rolling-horizon re-planning flips last week's decisions. Freeze the first periods, penalize deviations from the previous plan, and set terminal inventory targets. Measure nervousness explicitly (count of changed setups between consecutive plans) — otherwise the planning department will measure it for you.

The FL reformulation runs out of memory on long horizons. It carries $O(NT^2/2)$ variables; at $N = 200$, $T = 100$ that is a million w variables before presolve. Prefer the (l,S) cut loop on the standard model, restrict $w_{itu}$ to $u - t \le$ a max holding span, or aggregate periods.

The GA returns a plan that the validator rejects on capacity. The penalty weight is too small relative to setup savings, so infeasible individuals win tournaments. Raise the penalty, or make it adaptive (multiply by 2 whenever the generation best is infeasible); keep the validator as the final referee and report its verdict, not the fitness value.

Two formulations disagree on the optimal cost. Almost always an objective mismatch, not a solver bug: the inventory model charges $h_i s_{it}$ on end-of-period stock, the FL model charges $h_i (u-t)$ per unit — these coincide only with item-constant holding costs and zero initial inventory. Reconcile conventions (initial stock, end-of-horizon stock, time-varying $h$) and re-derive one objective from the other before suspecting anything else.

Tools & Libraries

Library When to use Note
gurobipy CLSP MIPs, cut loops, fix-and-optimize Fastest path to proven gaps; license required
HiGHS (highspy) Same models without a commercial license Good MIP performance; expect longer runtimes on hard CLSP
PuLP / Pyomo Solver-agnostic model definition Useful when the solver must be swappable; slower model build
OR-Tools CP-SAT Lot sizing fused with detailed sequencing Integer quantities only; shines on GLSP-like scheduling parts
numpy WW DP, decoder, GA, validator Everything in this skill except the MIPs runs on numpy alone
pandas Result/experiment tables One row per (instance, seed, method, objective, time, gap)

Output Format

A complete lot-sizing answer contains:

  1. Variant classification. One sentence: which model family (ULS / CLSP / CLSPL / small-bucket) and why, with the key data facts (N, T, utilization, setup times present or not).
  2. Model summary table. Variables, constraint families with counts, objective terms, and which reformulation/cuts are active.
Component Count Notes
x, s continuous 2·N·T production, inventory
y binary N·T setups
flow / link / cap constraints N·T + N·T + T named per family
(l,S) cuts added as separated root LP: before → after
  1. Bound and gap report. Standard LP bound, strengthened bound, best incumbent, proven gap, and runtime — e.g. "LP 2414.6 → +(l,S) 5397.3 → optimum 5571.5, 0.4 s".
  2. The plan itself. Per item: setup periods, lot sizes, end inventories; per period: capacity used vs available (flag periods above 95%).
  3. Validator verdict. Output of validate_clsp_solution — feasibility flag, recomputed objective matching the reported one, and the violation list (empty).
  4. For heuristic runs. Seeds, population/iteration budget, best/mean over ≥10 seeds, and gap to the best known bound — never a single-run number.
  5. Reproducibility artifacts. Instance generator parameters (seed, TBO, utilization), solver parameters changed from defaults, and library versions.

Questions to Ask

  • Is per-period capacity binding, and do setups consume capacity time as well as money?
  • How many items and periods, and are periods big buckets (weeks) or small buckets (shifts)?
  • Can setups carry over between adjacent periods? Are changeovers sequence-dependent?
  • Is backlogging or lost sales allowed, and at what cost?
  • Are there minimum lot sizes, batch multiples, or shelf-life limits on inventory?
  • Are costs time-varying, and is there nonzero initial inventory?
  • Is demand a firm forecast, or should the plan hedge against uncertainty?
  • Will the plan be executed once or re-solved in a rolling horizon — and how many periods are frozen?
  • What runtime is acceptable, and is a proven optimality gap required?
  • Is a Gurobi license available, or must everything run on open-source solvers?

Related Skills

  • dynamic-programming — for the recursion design behind Wagner-Whitin, the Florian-Klein capacitated DP, and state-space tricks when lot sizing appears as a subproblem.
  • cutting-planes-valid-inequalities — for separation machinery and user-cut callbacks when (l,S)-style cuts must run inside branch and bound instead of a root loop.
  • matheuristics — for fix-and-optimize, relax-and-fix, local branching, and how to budget MIP calls inside a heuristic loop on large CLSP instances.
  • milp-modeling-gurobi — for the gurobipy idioms used by every model here: constraint builders, parameter setting, status handling, and solution extraction.
  • stochastic-optimization — for lot sizing under demand uncertainty: scenario generation, two-stage extensive forms, and the L-shaped method behind static-dynamic strategies.