Milestones
List view
- Due by June 22, 2021•2/2 issues closed
* Test NYC capacity with new nodes added, aiming for at least 300. * Test LON capacity with OTP + VNO added, aiming for at least 450. * Validate 500 issue is addressed, potentially validate better transcoding performance.
Due by December 15, 2020•1/1 issues closedThe Livepeer API currently supports HTTP segment based transcoding, and users can create and manage API tokens on livepeer.com. There is user demand to interact directly with a Livepeer API with RTMP ingest, simple playback URLs and CDN support.
No due date- Due by December 8, 2019•14/14 issues closed
- Due by December 1, 2019•2/2 issues closed
- No due date•5/5 issues closed
- Due by November 17, 2019•7/7 issues closed
- Due by November 11, 2019•1/1 issues closed
- Due by November 10, 2019
- Due by November 3, 2019•3/3 issues closed
- Due by October 27, 2019•7/7 issues closed
- Due by November 1, 2019
- Due by October 18, 2019
- Due by October 14, 2019
- Due by October 6, 2019
- Due by October 6, 2019
- Due by September 30, 2019•1/1 issues closed
- Due by September 23, 2019•3/3 issues closed
- No due date
- Due by February 6, 2018•4/4 issues closed
Move to a more scalable p2p video network
Due by February 15, 2018•2/2 issues closedThis milestone reflects the [candidate functionality](https://github.com/livepeer/protocol/milestone/4) milestone in the protocol. The client implement the appropriate changes in the protocol.
Due by December 15, 2017•8/8 issues closedDeploy the oraclize verifier, make sure the verification cycle works.
Due by November 3, 2017•1/1 issues closed- No due date•7/7 issues closed
- Due by January 30, 2018•36/36 issues closed
Snowmelt is the first release phase of the Livepeer network. See https://medium.com/livepeer-blog/livepeer-network-phases-b196ab42264b Let's use this milestone to clearly scope what exactly needs to be included in this phase.
Due by February 14, 2018•50/50 issues closed- Due by October 6, 2017•27/27 issues closed
Goal: Community members should be able to 1) run transcoders, 2) broadcast video The soft launch period will help us get the bugs out of the system and give us some time to create tools needed for users.
Due by August 25, 2017•23/23 issues closed- Due by July 22, 2017•6/6 issues closed
- Due by July 21, 2017•8/8 issues closed