Skip to content

About

Mission Critical Advanced Scheduling (ALAP/ASAP) System | Minute-level accuracy for resource allocation and dependency management. Best for capacity-modeling, duration-estimation, slot-computation, tick-dispatch, quota-enforcement and order-timing

Topics

Resources

Stars

23 stars

Watchers

0 watching

Forks

Repository files navigation

ScriptPlan

ScriptPlan

Tests Probes Python Licence

A precise project scheduling engine with minute-level accuracy for resource allocation and dependency management. It reads projects written in the .tjp format.

Installation

pip install scriptplan

Quick Start

Report Generation (Unix-style)

# Generate JSON report to stdout
plan report project.tjp

# Generate CSV report
plan report --csv project.tjp

# Save to file
plan report project.tjp > output.json
plan report --csv project.tjp > output.csv

# Read from stdin
cat project.tjp | plan report
plan report - < project.tjp

# Pipe to other tools
plan report project.tjp | jq '.data[0]'
plan report --csv project.tjp | csvkit

# Process multiple files
for f in projects/*.tjp; do
  plan report "$f" | jq -r '.report_id'
done

Output Format (JSON):

{
  "data": [
    {
      "id": "project.task1",
      "start": "2024-01-01-09:00",
      "end": "2024-01-05-17:00"
    }
  ],
  "columns": ["id", "start", "end"],
  "report_id": "ea3f901dd6426dfa58288d945819c75485fd9ff1875db59def350f219e2d62ca"
}

Features:

  • Output to stdout (Unix philosophy)
  • Messages to stderr
  • SHA256 report_id over the rendered result, so it changes when the schedule does
  • Lowercase column names
  • No HTML metadata
  • No file pollution (uses temp directories)
  • Separate processes do not collide: temporary files and directories are unique per run

Python API

from scriptplan.parser.tjp_parser import ProjectFileParser

parser = ProjectFileParser()
project = parser.parse(open('project.tjp').read())

# Access scheduled tasks
for task in project.tasks:
    if task.leaf():
        start = task.get('start', 0)
        end = task.get('end', 0)
        print(f"{task.id}: {start} -> {end}")

Projects can be parsed and scheduled in parallel threads. Messages and the error count belong to the thread that produced them, so read get_message_handler_instance().messages in the thread that called schedule().

What is verified

Each behaviour below has a probe in audit/evaluations/ that drives ScriptPlan through its own API or CLI and asserts the result. They run as part of the test suite, and can be run on their own against an installed release:

audit/evaluations/run_all.sh

Time

  • Dates are read in the project's timezone and scheduled in UTC; reports convert back.
  • Resource shifts follow their own timezone across daylight-saving changes in both directions.
  • A working-hours interval that crosses midnight applies to the following day.
  • Slot size is derived from the times a project uses, so start 09:30 is honoured exactly and a shift of 08:13 - 11:59, 13:07 - 17:47 yields its true 8h26m a day. timingresolution overrides this.

Units

  • Calendar time (duration, gapduration) and working time (effort, length, gaplength) are distinguished, with working time derived from dailyworkinghours and yearlyworkingdays. m means months; min means minutes.

Resources

  • effort is person-time: two resources available in a slot contribute two slots of it. mandatory requires a resource for the task to progress at all; persistent keeps the one first chosen; alternative falls back.
  • dailymax, weeklymax, monthlymax, maximum and their min counterparts block at the cap and release in the next period. Periods are counted in the resource's own calendar, and a cap smaller than one slot is honoured exactly.

Scheduling

  • ASAP and ALAP, including chains that mix the two.
  • A task scheduled as late as possible ends by the earliest of its own end, the start of each successor (less any gap that successor asks for) and the project end. With none of these but a successor scheduled as soon as possible that states no start, it is scheduled as soon as possible instead, with a warning.
  • Contention is resolved by priority, then criticalness, then declaration order.
  • The declared project period is never rewritten. A task that does not fit is reported, with its name and the reason. A date stated outside the period is an error.
  • Scheduling the same project twice produces the same dates and the same bookings.
  • A stated start or end that the schedule cannot keep, and a task that would start before something it depends on finishes, are errors.
  • length and gaplength count the project's working time, not a resource's: a resource on longer hours does not shorten the gap.
  • maxgapduration, maxstart, minstart, maxend and minend are checked once the schedule is complete, and a violation is an error. (maxgaplength is not part of the syntax and is refused when parsed.)

Honesty

  • A project that cannot be scheduled exits non-zero and says why. A dependency cycle is rejected before scheduling, naming the cycle.
  • An attribute or reference the parser cannot place is an error, never a silent drop.
  • report_id is a SHA-256 of the rendered result, so it differs when the schedule differs.

Known limits

  • include, supplement, leaveallowance and statussheet are not implemented.
  • Output formats are JSON and CSV. ical, tjp, niku and MS Project XML are rejected at parse time rather than silently producing nothing.
  • Accounts are parsed but not yet modelled, so chargeset and charge record an amount without posting it anywhere.
  • A task reference is first looked up from the referring task's scope, one level up for each !. When that finds nothing but exactly one task in the project has that id, the reference binds to it, so depends !!pack inside delivery finds delivery.pack. When two tasks could be meant, the file is refused and both are named.
  • onstart on a dependency means start-to-start for a task scheduled as soon as possible: it may start once the predecessor starts. For a task scheduled as late as possible it means the task must finish before the predecessor starts, which is ScriptPlan's own reading.

Example Project

project "Manufacturing" 2025-07-01 +1m {
  timezone "Etc/UTC"
  timeformat "%Y-%m-%d %H:%M"
  scheduling alap
}

shift factory_hours "Factory Hours" {
  workinghours mon - fri 08:00 - 16:00
}

resource machine "Press" {
  workinghours factory_hours
}

task delivery "Product Launch" {
  end 2025-07-18-16:00

  task pack "Packaging" {
    effort 8h
    allocate machine
  }

  task assemble_b "Body Assembly" {
    effort 16h
    allocate machine
    depends !!pack { onstart }
  }

  task assemble_a "Engine Assembly" {
    effort 16h
    allocate machine
  }
}

task connection_setup "Logic" {
  task set_deps "Apply" {
    depends !delivery.assemble_a, !delivery.assemble_b
    precedes !delivery.pack
  }
}

taskreport output "output" {
  formats csv
  columns id, start, end
  timeformat "%Y-%m-%d-%H:%M"
}

This project schedules backward from the delivery deadline (ALAP mode). The scheduler:

  1. Anchors packaging to end at 16:00 on July 18
  2. Schedules both assembly tasks to complete before packaging starts
  3. Resolves resource contention (single machine) by sequencing assemblies back-to-back
  4. Respects weekend boundaries (Mon-Fri working hours)

Result:

delivery.pack:       2025-07-18-08:00 -> 2025-07-18-16:00
delivery.assemble_a: 2025-07-14-08:00 -> 2025-07-15-16:00
delivery.assemble_b: 2025-07-16-08:00 -> 2025-07-17-16:00

License

Apache-2.0

Acknowledgments

ScriptPlan reads the .tjp project file format. It contains no code from any other scheduler: the parser, the scheduling algorithms and the reports are its own.

Why ScriptPlan?

This scheduler is part of Highway Workflow Engine's worker capacity management system. I decided to open-source it for the community to benefit from its precise scheduling capabilities. Because it reads the established .tjp syntax, users can adopt ScriptPlan without learning a new format.

Yours, Farshid.

About

Mission Critical Advanced Scheduling (ALAP/ASAP) System | Minute-level accuracy for resource allocation and dependency management. Best for capacity-modeling, duration-estimation, slot-computation, tick-dispatch, quota-enforcement and order-timing

Topics

Resources

Stars

23 stars

Watchers

0 watching

Forks

Releases

Packages

Used by

Contributors

Languages